Key Dates & Accomplishments
Since its inception more than 12 years ago, the NBWRP has made significant progress in fulfilling its vision and implementing its Program. It has completed environmental and economic feasibility studies and solicited broad stakeholder input from potential recycled water customers, and established key partnerships to secure funding. In creating a model for maximizing limited water resources, it has demonstrated how a regional water reuse program can provide a long-term sustainable supply of water and receive support from state and federal agencies.
To sign up for automatic notification of key activities, please visit the Contact us page.
North Bay Water Reuse Program - Phase 1 Project Schedules
| Project | Agency Partners | Design Period | Construction Period |
|---|---|---|---|
| Novato South (Hamilton Field) | Las Gallinas Valley Sanitary District | October 2010 - April 2012 | September 2011 - September 2013 |
| North Marin Water District | |||
| Novato North | Novato Sanitary District | February 2011 - September 2011 | June 2011 - October 2012 |
| North Marin Water District | |||
| Novato Central | Novato Sanitary District | August 2016 - September 2017 | January 2018 - October 2019 |
| North Marin Water District | |||
| Sonoma Valley Recycled Water Project | Sonoma Valley County Sanitation District | May 2009 - June 2013 | May 2011 - September 2015 |
| Sonoma County Water Agency | |||
| Napa-Sonoma Salt Marsh | Sonoma Valley County Sanitation District | January 2011 - March 2012 | March 2013 - October 2013 |
| Sonoma County Water Agency | |||
| Milliken-Sarco-Tulocay Recycled Water Pipeline | Napa Sanitation District | December 2010 - September 2012 | April 2013 - October 2015 |
| Napa County | |||
| Napa State Hospital Recycled Water Pipeline | Napa Sanitation District | October 2005 - November 2011 | May 2011 - August 2012 |
| Napa County |
Key Dates:
- Early 2008: Began Environmental Impact Report (EIR) and Environmental Impact Statement (EIS) Studies.
- Summer 2008: Environmental Document Scoping.
- Spring/Summer 2009: Completed Environmental Studies (EIR/EIS).
- Fall 2009: Public Response to Environmental Reports and Response by NBWRA.
- May - December 2009: Final EIR/EIS prepared.
- December 2009: EIR/EIS Certified.
- January 2010 to 2019: Final Design and Construction of Phase 1 projects.
Timeline:
Completed Project Activities
- 2004: Draft Feasibility Report established service areas and scope of program
- 2006: Engineering Feasibility Report established facility needs
- 2007: Pursued grant funding opportunities, refined program scope, and selected consultants for environmental analysis and outreach
- 2008: Environmental analysis. Public outreach. Pursue grant funding.
- 2010: Began design and construction. Received authorization for $25 million in federal funding.
- Now: Construction of Phase 1 projects under way.
What We Are Doing Now
- Currently, Phase 1 projects are being implemented, with six recycled water projects in the design and construction phases. It is anticipated that Phase 1 projects will produce up to 5,500 AFY of recycled water.
- The study of the NBWRP Phase 2 has begun and includes potential new members: Marin County, Marin Municipal Water District, and the cities of Petaluma and American Canyon.