KEY DATES & TIMELINE

Below are listed some key project dates. To sign up for automatic notification of key activities,
please visit the Contact us page.
KEY DATES: |
| Early 2008: Begin Environmental Impact Report (EIR) and Environmental Impact Statement (EIS) Studies. |
| Summer 2008: Environmental Document Scoping. |
| Spring/Summer 2009: Complete Environmental Studies (EIR/EIS). |
| Fall 2009: Public Response to Environmental Reports and Response by NBWRA. |
| May - December 2009: Prepare Final EIR/EIS. |
| December 2009: Certify EIR/EIS. |
| January 2010 to 2012: Final Design and Construction. |
TIMELINE |
| Completed Project Activities |
| 2004: Draft Feasibility Report established service areas and scope of program |
| 2006: Engineering Feasibility Report established facility needs |
| 2007: Pursued grant funding opportunities, refined program scope, and selected consultants for environmental analysis and outreach |
| 2008: Environmental analysis. Public outreach. Pursue grant funding. |
| What We Are Doing Now - |
| Moving ahead with full-scale studies; engineering, financial, and economic |
| Active effort to support this regional project with significant federal grant funding |
| What's Next |
| 2010: Begin design. Obtain federal funding. |