THE NORTH BAY WATER RECYCLING PROGRAM - PROJECT DESCRIPTION
Phase 1 and Alternatives | Phase 1 Marin County | Phase 1 Sonoma County | Phase 1 Napa County | Three Alternatives
| 83 miles of pipelines | + 56 miles of pipelines | = 139 miles of pipelines | + 14 miles of pipeline | = 153 miles of pipeline |
| 1,000 acre-feet of new storage | + 1,200 acre-feet of storage | = 2,200 acre-feet of storage | + 0 acre-feet of storage | = 2,200 acre-feet of storage |
| 2,200 horsepower of pumping | 1,300 horsepower of pumping | = 3,500 horsepower of pumping | = 1,300 horsepower of pumping | = 4,800 horsepower of pumping |
| 8 million gallons per day of treatment capacity | + 8 treatment capacity | 16 million gallons per day of treatment capacity | + 5 treatment capacity | 21 million gallons per day of treatment capacity |
| 6,700 acre-feet recycled water available | + 4,500 acre-feet of recycle water available | = 11,200 acre-feet of recycle water available | + 1,600 acre-feet of recycle water available | = 12,800 acre-feet of recycle water available |